Construction of Mapleton’s new municipal maintenance facility is on track to come in within budget after council approved tenders for the project at a special meeting on Aug. 14.
At the meeting, council authorized project managers Chamberlain Construction Services Ltd. to award the following tenders:
– pre-engineered building tender package to Comsteel Building Solutions for $754,295;
– administration structural steel, misc. metals and catwalk tender packages to Vandepas Welding Limited for $148,159;
– concrete slab on grade tender package to Apollo Concrete for $348,440;
– cranes tender package to Munck for $38,809;
– well and septic system to Highland Water and Well Drilling for $75,100;
– overhead doors to Mapleton Flooring and Windows for $181,296;
– concrete foundations to Able Concrete Flooring for $184,405;
– masonry to Konia Masonry for $136,100;
– flat roofing to Nedlaw Roofing for $59,055;
– ceramic tile and base to Mapleton Flooring and Windows for $24,261;
– sprinkler system to Troy Life and Fire Safety for $104,300;
– HVAC and plumbing to Kittel Mechanical for $647,650; and
– electrical tender package to Avon Electric Co. Limited for $311,500.
Bid prices do not include HST.
In a written report, public works director Brad McRoberts noted other bid packages under review will follow at a later date, once Chamberlain Construction Services has completed a review.
“From the project budget analysis, the original budget of $5,155,542 appears sufficient,” the report states.