The township’s new municipal maintenance facility is on target for completion this August.
CAO Brad McRoberts reported at the April 26 meeting that the overall project is about 50 per cent done and final completion remains projected for August.
While it will “depend on how ongoing work is proceeding,” said McRoberts, the township “may have some occupancy in advance of that.”
With tenders awarded for all facets of the project, McRoberts reported it is currently running about $62,000 under budget.
The project budget is $5,155,542 with a committed cost to date of $5,092,855 and a remaining contingency of $119,975.
“It’s good to see that we’re coming in under budget or on budget and on schedule,” said Mayor Neil Driscoll.