Last week’s column took the story of the building of the Conestogo Dam to the fall of 1956. Contractor C.A. Pitts had expected the dam to be complete by then, but political squabbling and an extremely wet summer had delayed work.
At times, the big construction job seemed to be jinxed. A worker crashed and was killed one morning while driving to work. In November 1956, there was another fatality, when a gravel truck hit the car driven by a land buyer for the Grand River Conservation Commission.
Through the late fall and early winter, crews were busy clearing trees and brush from the area that would soon be flooded. It was a large job: several woodlots had to be removed.
Reeve Phil Rowland called Maryborough council into session again on Dec. 17, furious over the removal of a couple of bridges and dozens of roadside trees without notification of the township. Council passed unanimously another resolution condemning the GRCC.
The GRCC members toured the area early in January 1957, following a lunch in Fergus. First stop was the old Elora quarry, by then owned by the Commission, and idle for a quarter of a century. The GRCC had reopened the operation as a source of limestone rip-rap rock to be used as a facing on the earth portions of the dam. From the quarry the group moved on to the dam.
C.A. Pitts had continued work as long as possible into the fall of 1956, and had managed to get almost all the concrete work completed before shutting down for the winter. As well, most of the heavy earth moving was completed thanks to favourable late fall conditions.
In mid January, C.A. Pitts crews dismantled the largest piece of equipment, a 105-ton shovel, and loaded the components onto flatcars at Linwood’s Canadian Pacific station. The destination was another Pitts contract, on the St. Lawrence Seaway.
Frustration was evident in the attitudes of GRCC members when they met on Jan. 18, 1957.
Arguing over roads had occupied 18 months, and the entire 1956 construction season had been lost for building and rerouting roads. They denounced the “excessive and costly demands of the townships,” and were annoyed at the slowness of provincial officials in making decisions on matters referred to them.
The project was headed to exceed the $5.4-million estimate, but the federal government advised that it would provide no additional funding.
Emboldened by a legal opinion that stated the GRCC had the right to close and relocate roads without municipal permission, members proceeded with the letting of tenders for the major road work that had been advertised late in 1956.
R.A. Blyth construction offered the lowest bid, at $458,000. The GRCC was determined that work would proceed, with or without agreements with Maryborough and Wellington County council.
A month later the GRCC members discussed a request from the provincial government to increase the size of the reservoir, based on data collected during Hurricane Hazel in October 1954. Talk ended when the engineers advised that it was impossible to change the design of the dam at such an advanced stage without a prohibitive cost overrun.
There were a couple of pieces of good news. GRCC engineer Peter Rogers reported that the tree clearing operations during the winter came in at $108,000, which was $7,000 under estimate. And the land buyers reported that agreements had been reached on all but three parcels.
On March 4, the GRCC appointed a committee consisting of chairman Marcel Pequegnat, E.F. Roberts of Brantford, and mayor L.F. Dreyer of Kitchener, with a mandate to bring a final resolution to the outstanding road issues.
Two days later, Maryborough Reeve Rowland gathered together his supporters at a meeting in Guelph. They decided to take their issues an complaints to Highways Minister James Allan. He would be the arbitrator. Pequegnat had already been in touch with him.
The result was an agreement worked out in early June, recommending the closure of several sections of road, the construction of three new roads, and raising and improvements to several other stretches. It seemed like the final resolution.
The agreement provided for a paved road surrounding the new lake and Conestoga Dam, and roads to serve all remaining farms. The plan facilitated good local connections and allowed through traffic to bypass the area. Local MPPs Fred Edwards and John Root assisted with lobbying at Queen’s Park. The province and Conservation Commission would pay for all the costs of the road work.
The road agreement resulted in changes to the contract awarded to R. A. Blyth. Due to the death of a supervisor, little work had been done. At the request of Blyth, the GRCC approved the subletting of the work to Sir Lindsay Parkinson (Canada) Limited.
Sad days for oldtimers came on March 2 and 3, when the Royal Canadian Engineers used Hollen and the surrounding area for a war simulation. That was the end for most of the buildings in the Hollen area.
With heavy work on course to be largely completed during the summer and fall of 1957, the GRCC dealt with a number of smaller items. Canadian Comstock submitted the lowest of seven bids for the electrical equipment at the dam, at $27,600.
Ronald Osgathorpe was hired as operator at the dam. He would live in the former residence of Myrtle Mitchell, which would also house the office for the dam. Recreation and reforestation loomed ever larger in the picture. During the summer, the GRCC decided to purchase an additional 450 acres in the vicinity of the new lake.
After lengthy negotiations with Peel Township, Reid Bros., of Elmira, who had the contract to haul the limestone from the Elora quarry, agreed to be responsible for any damage to township roads resulting from the heavily loaded trucks.
The construction site continued to lure tourists to the new dam, resulting in heavy weekend traffic. That pleased Russ Lyons, of the Drayton Restaurant, who expanded his kitchen to cope with overflow crowds. Some local businessmen expected a permanent boost to the local economy through tourism – an outcome that few had anticipated at the beginning of construction.
Project manager Art Cantle, in a report in July, expected the dam to be completed by the end of September. The latest frustrations had been quicksand and an artesian well. All the problems had put completion a year later than had been planned originally. Nevertheless, earlier fears of major cost overruns did not materialize. By sharpening their pencils, engineers were able to bring the project in at the most recent estimate of $5.4-million.
Employment on the site dropped below 100 during the summer of 1957. It had peaked at more than 150 a year earlier. Altogether, the C.A. Pitts crews had poured 95,000 cubic yards of concrete and had moved 1,200,000 cubic yards of earth.
Though Highways minister James Allan had mediated a roads agreement, Maryborough council was far from happy with it. They discussed it at length in August, and planned further discussions later in the fall.
The most recent estimate of a September completion proved to be optimistic. The major job yet to do was the installation of the gates. Above the dam there was still plenty to do, including final agreements for some of the land. But a full completion of the project was at last on the horizon.
Next week: Final work, and the dam goes into service.