Conestogo Dam was ready to handle 1958 spring thaw

Last week’s column carried the story of the construction of the Conestogo Dam up to the end of the summer of 1957. This week’s installment conti­nues the account as construc-tion wound down in the fall of that year.

C.A. Pitts and Company com­pleted concrete work on the big project during the first week of October. By then the earth embankments were large­ly in place, thanks to the de­ployment of four scrapers, 15 dump trucks, five tractors, two graders, and three power shov­els. The amount of earth moved was immense. As soon as the embankment was packed down, Reid Brothers, of El­mira, brought in truckloads of facing limestone from the Elora Quarry.

Work on the various road projects continued through the fall of 1957. Sir Lindsay Park­inson (Canada) Limited, the chief road contractor, had 22 men at work on the roads, plus another seven at a gravel crush­ing plant. H.G. Acres & Co., the project engineers, had a resi­dent engineer and staff of seven still on the project. 

The one big job remaining was fitting the big control gates into place. Those were massive steel assemblies, 15 by 22 feet, and weighing 22 tons each. Putting them in place was a deli­cate operation: they could easily damage the concrete work if they struck it during placement. Canadian Com­stock workmen had the motors and controls ready for testing when the gates were in place in early November.

A series of tests followed, and they would continue over the winter. The operator allow­ed the water to rise to a level of 20 feet, and then the gates were opened, permitting a flow of 4,000 cubic feet per second.

The members of the Grand River Conservation Commis­sion visited the site on Nov. 20. They were pleased to note that work was virtually complete. Later that day they learned that, despite two floods during con­struction and other problems that had held up completion for more than a year beyond the original schedule, the project would still come in within the $5,400,000 estimate.

The entire project, including land acquisi­tion and road realignment and construction, would boost that total to nearly $8,000,000.

By late fall, the C.A. Pitts had moved most of its machin­ery and men to a project on the St. Lawrence Seaway, but there were plenty of small tasks to tidy up over the winter, and some that had to be deferred to spring.

GRCC members were re­lieved to learn at their meeting on Feb. 26, 1958 that the pro­ject was virtually complete. One outstanding matter was that Maryborough Township had not yet signed its agree­ment with the Commission, and was raising new issues with every meeting. Reeve Phil Rowland had opposed the dam from the beginning, and the posi­­tion of his council had, if anything, hardened over the preceding four years.

Commission chairman Mar­cel Pequegnat blew his top: “We conceded many of the demands made by them for additional expenditures for road and bridge work … Negotiations have been most difficult and protracted … There appears to be no end to the demands.”

He recommended that the GRCC refuse to authorize any further work beyond what was already approved.

A major decision that day was to place the new dam in service to catch the spring runoff. When that news reach­ed Maryborough its council became infuriated, as did MPP John Root. There were still some outstanding disputes over land acquisition, in addition to Maryborough’s lengthy list of demands over bridges and roads.

Four landowners had not agreed on a price, and those cases were destined for arbitra­tion. The GRCC had decided to expand the acquisition of land around the lake. Their pur­chas­es now totalled almost 5,500 acres, costing them about $550,000.

The harsh condemnation from the Conservation Com­mis­sion seems to have tem­per­ed the opposition of Mary­borough council. They listened favorably to a delegation from Kitchener with plans for a Scout and Guide camp on a 42-acre property near the lake, purchased by the Gowdy De­partment Store, and pledged full cooperation.

The Commission decided that the official completion date would be Oct. 15, 1958. That allowed plenty of time for the final work on the dam, the settling of land issues, and the completion of the road work.

In March, Maryborough council was surprised to re­ceive a cheque for $10,000 from the Grand River Con­ser­vation Commission, to com­pensate the township for the loss of roads and bridges around the new reservoir that were still on the list of out­standing issues. In addition, the Commission would bankroll the cost of some new road links and upgrades.

The cheque and promise soothed the council to a large extent. By then, they realized that there was nothing they could do to slow down the pro­ject, though Reeve Row­land was still upset at they way he felt the township had been misled and mistreated during the previous four years.

The thaw and runoff in the spring of 1958 was a very light one, and did not provide much of a test for the new dam. The new plan was to allow the water level to rise over the rest of the spring and summer of 1958.

Meanwhile, the road work continued. The last of the big contracts went to Cox Con­struc­tion, of Guelph, for $115,000 of work to the Peel-Maryborough Town Line and the new link that would carry the route over the dam, and for $113,000 of paving work to that route and portions of other roads.

Next week: tidying up the loose ends, and dealing with cottage lots.

 

Stephen Thorning

Comments